Site Commissioning Steps

  1. Devices Tab - Click "Discover Microinverters".
  2. Layout Tab - Lay out modules.
  3. Communication Tab - Click "Check Communication".
  4. Site Commissioning Tab - Commission site.

PV Supervisor Management Console

Important

 

 

You are using an unsupported browser.

 

Please use the Chrome or Firefox browser for full feature compatibility.

 

Layout Save

 

When you have completed and saved the site layout, proceed to the Communication Tab.

 

If you do not save the site layout before exiting this tab, all progress will be lost.

 

Do you want to save the site layout?

 

 

Last Scan:    

Microinverters Discovered:    

866-894-1505
DevicesStatusAddress
 

Confirmation

 

Are you sure you want to start Discovery?

 

This operation will replace or modify the existing PV Supervisor configuration.

 

Confirmation

 

Are you sure you want to remove the microinverter?

 

 

Notice



An extra installation step is temporarily required to ensure discovery of all Gen2 AC modules in the array.
Click OK to confirm that you have completed this step.



Immediately before performing AC module discovery:

1)    Ensure that the AC module system is properly installed and connected to the service panel

2)    Power cycle the circuit breaker for each SunPower AC module branch circuit
        a. If the circuit breaker is ON, turn it OFF for 10 seconds and then turn it ON again
        b. If the circuit breaker is OFF, turn it ON for 10 seconds, then turn it OFF for 10 seconds and then turn it ON again

3)    Perform module discovery



Discovery Details



NOTE: You MUST enter total count of microinverters installed on site to proceed with Discovery





Use this option for new installations, adding panels to the site, and completing microinverter RMAs



CAUTION: This option will erase current module layout

Use this option for extensive site maintainence only





Notice



You MUST enter total count of microinverters installed on site to proceed with Discovery



Scanning for Devices

 

 

 

Last Checked: Never   

StatusAddress

 

 

 

 

Click the Check Communication button.
When Internet Communication status is shown as Working proceed to the Site Commissioning Tab.

Devices Scan

 

 

 

Administration

 

PV Supervisor S/N:    

 

SSH   

Success

 

The PV Supervisor successfully
established an SSH connection

 

Confirmation

 

Are you sure you want to restart the PV Supervisor?

 

 

Success

 

The PV Supervisor was
successfully restarted

 

Error

 

Please restart the application

 

Important

 

All rows displaying have been discovered proceed to the Layout tab.

 

For any microinverter (module) that you installed but that does not display, re-check the cable connections and then click Discover Microinverters again.

 

Microinverters with a Working or Has Not Reported status are ready for layout and then commissioning.

 

Microinverters with a Disabled status are also ready for layout and commissioning, and afterward will automatically receive a firmware upgrade.

 

Microinverters with an Error status are also ready for layout and commissioning, but require a cable check and possibly additional diagnostics.

 

Location

 

 

 

Signal strength below threshhold.
Please click the "Run Signal Strength Test"
button to perform further analysis.

 

Confirmation

 

 

 

Checking Internet Communication

 

 

Admin Sign In

 

Installer Sign In for system configuration and administrative changes

 

Password